Question 1
Which statement is one of the four values of the Agile Manifesto?
Show answer & explanation
Correct answer: B - Customer collaboration over contract negotiation
10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
The ASF exam has 40 questions and runs 1 hour.
These 10 free ASF questions are organized by exam domain, so you can see how each part of the EXIN Agile Scrum Foundation (ASF) blueprint is tested. Reveal the answer and explanation under each question.
Which statement is one of the four values of the Agile Manifesto?
Correct answer: B - Customer collaboration over contract negotiation
Traditional projects fix the scope and let time and cost vary. In an Agile project, which of these is normally allowed to vary instead?
Correct answer: C - Scope
During the Sprint, one Developer works alone on a task and does not finish it. Who is accountable for the unfinished work?
Correct answer: A - All of the Developers together
What is the purpose of the Daily Scrum?
Correct answer: D - To inspect progress toward the Sprint Goal and adapt the plan
When does Product Backlog refinement take place?
Correct answer: C - Continuously, as an ongoing activity during the Sprint
The Product Owner estimates a Product Backlog item at two days. The Developers estimate five days. Which estimate is used?
Correct answer: B - The Developers', because they perform the work
Halfway through a four-week Sprint, the Developers conclude they need three more days to finish the selected work. What happens to the Sprint?
Correct answer: A - It ends on the planned date
All of the following are appropriate factors for ordering the Product Backlog EXCEPT:
Correct answer: D - Developer availability
Which statement about the Sprint Review is correct?
Correct answer: B - Stakeholders attend, and the Product Backlog may be adjusted
A Scrum Team has completed 72 story points over its last 8 Sprints. The remaining work is estimated at 56 story points. Approximately how many more Sprints are needed?
Correct answer: C - 7
The ASF exam also covers these domains. Drill them in the full free practice test:
The full bank has 1,020 more ASF questions with explanations.
Continue in the free practice test →
View plans